Today, the former Palace of Communication in Madrid is the seat of Madrid’s municipal council. The building in the heart of Madrid, which was completed in 1919, covers an area of 12,200 m2 and 30,000 m2 including the outside grounds. The building needed to be retrofitted with an automatic fire protection system.
Challenges
The central location, the associated lack of space, the very limited installation space and the need to install the system during ongoing operation – not to mention the fear of water damage – excluded the installation of a conventional sprinkler system. The high rooms and halls constituted further challenges.
The FOGTEC water mist solution